Full Service Condo Remodels

Maui Remodels is a full licensed contractor. We  take care of everything from Start to End. Our planning stage for a full condo renovation is typically 2-3 months.

We will help with design, provide measurements and give directions on the Island supplies we prefer. We exceed all the requirements of your association.

Arrow
Arrow
Slider

Arrow
Arrow
Slider

Arrow
Arrow
Slider

First Step For Getting Your Condo Remodeled

There are few things that need to happen right away when you want to start a full condo remodel. Those would be Determining the long lead items and getting them ordered.

Below is a list of typically our costumers order in advance

• Cabinets 6-8 weeks

• Luxury Vinyl Planks 2-3 weeks

•Tile 3-6 weeks

•Shower and Kitchen Fixtures 2-4 weeks